Background
Enel North America (ENEL) is electrifying the economy and advancing a just transition to 100% renewable electricity. In April 2024, ERCOT implemented a requirement for all Inverter-Based Resource (IBR) entities to submit As-Built PSSE and PSCAD models before achieving commercial operation date (COD). With construction and commissioning complete, the Fence Post BESS project is prioritizing the development of these models to meet this requirement and ensure timely COD.
Challenge
Developing As-Built PSSE and PSCAD models is a complex and critical process. Beyond updating steady-state parameters (e.g. equipment ratings and impedance), the dynamic models must be carefully parameterized with the as-commissioned ratings. The primary challenges lie in two key areas: Ensuring the models precisely reflect the final As-built site configuration and even more critically, meeting ERCOT’s stringent model quality test (MQT) requirements.

Approach
EPE planned to collaborate closely with ENEL to gather field settings from each Original Equipment Manufacturer (OEM), ensuring the PSCAD model was accurately parameterized with as-commissioned data.

Solution
EPE conducted the required ERCOT MQT, proactively identifying and recommending necessary field setting adjustments to ENEL to optimize ride-through performance and secure successful MQT results. To finalize the process, EPE developed the As-Built WECC generic PSSE model and benchmarked it against the PSCAD model, verifying consistency across both platforms.
DownloadWant to learn more about our solutions?
When you partner with EPE, you get an experienced team dedicated to providing you with tailored solutions and expert guidance.
Please fill out the form to the right, and a member of our team will be in touch.