EPE's Integral Role in ENGIE SOLAR's Solaire Holman Project

Background

The Solaire Holman project in Brewster County, Texas is ENGIE SOLAR's first project in ERCOT. The 50 MW single-axis-tracking PV array consists of twenty-six (26) KACO BluePlanet 2200 TL3 skid-mounted power stations. The project's Point of Interconnection (POI) is American Electric Power (AEP's) 69 kV Alpine to Fort Stockton transmission line. The initial POI is a temporary line tap and, six months after COD, the POI will shift to a new AEP switching station connecting both the Alpine to Fort Stockton and the Alpine to Barilla Junction transmission lines.

EPE case study featured image
Single Testimonial Line Mesh
"Technical support from the EPE team was invaluable. The interface with our project partners was seamless, and the interconnection process was effortless."
Matt Held, VP Asset Development, Engie Solar

Approach

First, EPE performed a transmission export analysis for this project and kicked off the interconnection process with the Electric Reliability Council of Texas (ERCOT). EPE modeled two SO MW phases each connecting to separate 69kV circuits as well as connecting to both circuits through a new switching station. On behalf of the client, EPE prepared the necessary applications and studies.

EPE case study image

Solution

First, EPE performed a transmission export analysis for this project and kicked off the interconnection process with the Electric Reliability Council of Texas (ERCOT). EPE modeled two SO MW phases each connecting to separate 69kV circuits as well as connecting to both circuits through a new switching station. On behalf of the client, EPE prepared the necessary applications and studies.

Secondly, EPE developed specifications for the step-up transformer and for the substation EPC solicitation, evaluated bids and advised the client in negotiating and awarding contracts. EPE served as owner's engineer, working with the engineer-of-record, providing technical support and reviewing all calculations, drawings and studies. EPE was responsible for ensuring that the project complies with interconnection standards for AEP, ERCOT and good utility practices.

Currently, EPE is providing support for testing and commissioning and coordinating ERCOT approvals leading to commercial operation in 2017.

EPE led this project from the planning phase to the design/engineering/ procurement phase, all the way to getting the project shovel ready and acted as owner's engineer throughout the construction phase. The project was energized in March 2017 and began commercial operation in April 2017. The project will make a final permanent interconnection in October 2017.

Download

Want to learn more about our solutions?

When you partner with EPE, you get an experienced team dedicated to providing you with tailored solutions and expert guidance.

Please fill out the form to the right, and a member of our team will be in touch.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.