ERCOT's large load interconnection process reached a major milestone this month with Board approval of PGRR145 and NPRR1325, formally establishing the Batch Zero Study Process framework.
At the May 20 Technical Advisory Committee (TAC) meeting, ERCOT presented the proposal incorporating stakeholder feedback received through May 18. It received unanimous TAC approval, with one abstention, before advancing to the ERCOT Board. On June 1-2, the Board unanimously approved the final Batch Zero framework under PGRR145 and NPRR1325 with an effective date of July 10, 2026. The final step in the approval process is consideration by the Public Utility Commission of Texas (PUCT).
.png&w=3840&q=75)
Large Electronic Loads (LELs) that previously submitted Composite Load Models (CMLDs) will need to transition to EPRI's PERC1 format. Developers should also confirm that submitted Dynamics Working Group (DWG) surveys remain aligned with current project designs and operating assumptions.
The Batch Zero framework introduces two important classifications for large load projects.
With the July deadlines approaching, developers should be focused on:
With several key deadlines approaching, developers should verify their studies, models, surveys, and registration strategies remain aligned with the new requirements under PGRR145 and NPRR1325. To find out how EPE can support you with PERC1 model updates, DWG survey revisions, Batch Zero readiness reviews, and strategic evaluations of PCLR and WLPUN participation options, contact our team using the form below.
We're here to help.
When you partner with EPE, you get an experienced team dedicated to providing you with tailored solutions and expert guidance.
Please fill out the form to the right, and a member of our team will be in touch.