In mid-January, EPE attended a workshop where CAISO presented its Final Track 3 Proposal, part of the 2023 Interconnection Process Enhancements implementing FERC Order 2023 requirements. This session allowed stakeholders to engage directly with CAISO by asking questions, providing recommendations, and requesting clarifications on the presented materials. Below are the key proposals and their implications.
Allocation process to allow generators to interconnect without triggering long lead-time upgrades.
New priority groups and scoring criteria for TPD allocations starting in 2027.
Extended deadlines for financial security postings for certain projects.
Deferred TPD attempts and reserved transmission capacity for qualifying resources.
These changes are designed to support the growth and integration of renewable energy projects by making the interconnection process more efficient and equitable. They will also provide greater flexibility and support for renewable energy projects, facilitating their successful integration into the grid. The final proposal and stakeholder call will happen later this month.