On July 11, 2025, ERCOT issued an updated Market Notice reinforcing restrictions on new inverter-based generation at transmission voltage in Hill County, Texas, located between Waco and Fort Worth. The restrictions will also apply to the nearby 345-kV area, known as the SAMSW Generic Transmission Constraint (GTC).
ERCOT’s evaluation confirmed that allowing any new inverter-based resources, regardless of dispatch level, presents an unacceptable stability risk under certain multiple contingency conditions. Consequently, any proposed generator that has not yet received Part 2 approval must:
These requirements apply even to projects already in the interconnection or modification process. ERCOT is currently evaluating possible transmission upgrades that could allow for eventual removal of the constraint. Once a solution is identified, ERCOT will update the SAMSW GTC methodology and publish the changes to the ERCOT MIS Secure Area.
If you are pursuing or considering interconnection in the Hill County/SAMSW area, especially if your project includes inverter-based generation, this Market Notice could delay your synchronization timeline unless stability concerns are proactively addressed. Delays in securing Part 2 approval can cascade into schedule slippage and unwanted financial impact.
Our team can support you with targeted technical studies and interconnection guidance to help preserve your timelines and avoid surprises. Contact us to assess your risk and help you plan the right path forward.
If your project aims to synchronize in Q2 of 2026, you must plan now in order to meet the November 1st, 2025 QSA deadline. Under the requirements established by PGRR112, all necessary QSA prerequisites must be satisfied by September 17, 2025, to be included in the QSA.
What you will need by September 17:
Missing this deadline will delay your project’s synchronization eligibility by a full year to Q3 of 2026.
Don’t let tight timelines catch you off guard. At EPE, our expert team is here to support your interconnection journey.
The South Texas Electric Cooperative (STEC) is seeking to secure up to 500 MW of firm, dispatchable capacity in the form of dispatchable generation facilities or long-term power purchase agreements, tolling agreements, or other long-term contract structures.
STEC will consider all generation technologies and fuel types, provided the assets are located within the ERCOT region, ideally near or within the service territory of one of STEC’s nine-member cooperatives.
Key Parameters:
This RFP represents a significant opportunity for developers and asset owners. With a required COD of no later than December 1, 2028, time is of the essence for projects that are not yet online. Developers must consider ERCOT interconnection timelines, including modeling, stability assessments, and site-specific constraints that can affect both project viability and schedule.
At EPE, we support clients throughout the full lifecycle of ERCOT project development, from feasibility through commercial operation. For generation developers pursuing opportunities under this RFP, EPE’s support covers a broad range, including but not limited to:
If you are evaluating a dispatchable project for submission under this RFP, reach out to EPE today. Our technical experts are ready to help position your project and explore timeline options.
As ERCOT continues adapting to changes brought by the One Big Beautiful Bill Act (OBBBA), developers face an evolving interconnection process. If you have not yet, check out our OBBBA article for a breakdown of key impacts on queue management, hybrid projects, and shared interconnection requests.
We're here to help.
When you partner with EPE, you get an experienced team dedicated to providing you with tailored solutions and expert guidance.
Please fill out the form to the right, and a member of our team will be in touch.