
.png&w=1200&q=75&dpl=dpl_9cWKpif7SVaBVSkZw3dRxjWAtLtd)
As 2026 begins, developers with transmission-level generation projects in ERCOT face a major regulatory shift under the Standard Generation Interconnection Agreement (SGIA).
The Public Utility Commission of Texas (PUCT) updated Rule §25.195, changing how Transmission Service Providers (TSPs) recover the cost of Transmission Interconnection Facilities (TIF). While effective in 2024, the most meaningful impacts apply to SGIAs executed after December 31, 2025.
The updated rule establishes a two-tier cost responsibility framework:
Any TIF costs exceeding these allowance amounts are the generator’s responsibility.
ERCOT’s updated SGIA template, effective January 1, 2026, reflects the allowance framework and introduces Notice to Proceed and Construction Authorization Dates, along with some other changes.
Additionally, TSPs must now report interconnection cost data to ERCOT. ERCOT will publish annual summaries starting in 2027, providing market-wide visibility into interconnection costs, contributions in aid of construction, and above-allowance expenditures.
These changes raise the stakes for timing and cost planning. Understanding the new rules is critical for project economics, financing, and site strategy.
Electric Power Engineers is tracking implementation and advising developers on navigating these changes. If you are planning a transmission-level generation or storage project in 2026 or beyond, early alignment can prevent costly surprises.
To discuss how these updates impact your interconnection strategy, contact our team using the form below.
We're here to help.
When you partner with EPE, you get an experienced team dedicated to providing you with tailored solutions and expert guidance.
Please fill out the form to the right, and a member of our team will be in touch.