ERCOT’s third NOGRR245 workshop confirmed what many in the market suspected: exemption and extension requests are proving to be more challenging than expected — and the clock is ticking.
In April, 427 resources filed for relief. ERCOT’s review found that not a single submittal fully met all requirements. With the September 15, 2025 deadline fast approaching, developers, asset owners, and consultants have a narrow window to address critical gaps.
ERCOT’s latest workshop highlighted several key items:
These requirements significantly increase the technical and procedural workload to accurately file for extension or exemption requests.
The most common deficiencies highlighted in ERCOT’s latest workshop include:
Any of these gaps can trigger outright rejections that could require resources to comply with the NOGRR245 requirements even if they cannot.
At Electric Power Engineers, we’ve guided thousands of projects through ERCOT’s evolving rules and technical standards. Our team brings:
Because we’ve been involved in ERCOT market changes from the start, we can identify and resolve compliance gaps before they become costly roadblocks.
If you have an extension or exemption pending — or you’re not confident your submittal will pass ERCOT’s tightened review — now is the time to take action.
The September 15 deadline leaves no margin for error. Let’s map your compliance path now so your project stays on track.
Contact my team below to schedule a rapid compliance assessment.
We're here to help.
When you partner with EPE, you get an experienced team dedicated to providing you with tailored solutions and expert guidance.
Please fill out the form to the right, and a member of our team will be in touch.