Large Electronic Loads (LELs), such as data centers and cryptocurrency mining facilities continue to scale rapidly across ERCOT, prompting new reliability standards for interconnection and energization. ERCOT’s proposed NOGRR 282, alongside NPRR 1308, formalizes voltage and frequency ride-through expectations for LELs, responding to recent grid events where these loads tripped or rapidly reduced consumption during disturbances, even when protection systems operated as designed.
As LELs grow in scale, ERCOT is prioritizing ride-through performance to prevent voltage instability, frequency excursions, and potential System Operating Limit (SOL) violations.
Under NPRR 1308, ERCOT distinguishes between Large Loads and Large Electronic Loads:
ERCOT’s LEL definition intentionally focused on computational loads, following extensive engagement with developers and equipment manufacturers to better understand ride-through capabilities.
NOGRR 282 introduces new sections to the Nodal Operating Guides:
An LEL must comply with these requirements unless one of the following conditions was met on or before November 14, 2025:
Projects that do not meet these exemption criteria are subject to the new ride-through standards as part of their energization and operational approval process.
Section 2.6.4 establishes frequency ride-through performance for LELs. LELs are expected to remain connected through defined frequency excursions, rather than tripping offline in response to routine grid events. ERCOT’s review focuses on how load controls, protection settings, and power electronics respond to frequency deviations that could otherwise amplify system-wide events.
Section 2.14 details voltage ride-through performance expectations. LELs must demonstrate the ability to stay connected through specified voltage depressions and recovery profiles. Even if a facility is technically compliant with existing standards, ERCOT may flag concerns if simulations show that load tripping could lead to System Operating Limit (SOL) violations or broader reliability risks, especially for inverter-based and power-electronic-dominated loads.
Key Points:
If ERCOT determines that an LEL failed to meet frequency or voltage ride-through requirements:
Until NOGRR 282 is fully approved and implemented, ERCOT has established a structured transition framework for Large Load energizations occurring between late 2025 and September 2026. During this period:
ERCOT plans to introduce a model quality test process for VRT verification as a future condition for energization approval.
NOGRR 282 signals a clear shift in ERCOT’s expectations for how LELs interact with the grid during system disturbances. Ride-through capability, accurate dynamic modeling, and early engagement with ERCOT and TDSPs are now central to energization readiness and operational approval.
Electric Power Engineers (EPE) actively participates in ERCOT’s stakeholder processes and working groups. We support large load developers with:
As ERCOT formalizes these requirements, early technical alignment is critical. To discuss how these evolving rules may impact your project, contact EPE using the form below.